PSERC
04/06/04
8
Recommendations
•Strategic (#5): Need to improve relay protection schemes and coordination •Technical (#8): Improve system protection to slow or limit the spread of future cascading outages:
•   a.) better application of Zone III relays
•   b.) selective use of under-voltage load shedding
•   c.) revision to the criteria for slowing/limiting propagation of cascading failures