This talk is partially based on the IEEE Proc.  paper, Nov 2005
19
Dependence of feasible interconnection transfer on scheduling practices
•Base case for the given NPCC system in 2002 and the 2007 projected load [3]
•Case #1-the same, except the entire real power generation was re-scheduled in order to support an increased wheel from PJM (Alburtis) through NYISO to  IESO (Milton) –the maximum feasible wheel 1,200MW
•Case #2-the wheel from PJM  (Waldwick) through NYISO to IESO (Milton) –the maximum wheel feasible 100MW
•NOT SUFFICIENT TO ONLY SPECIFY NET TIE LINE FLOWS